F3 Networks is a Canadian company that builds fiber infrastructure for growing communities. We build the network that internet service providers can use, helping prepare neighbourhoods for future connectivity without asking homeowners to pay for the infrastructure themselves.

Our team brings decades of telecom and fiber construction experience from projects across Canada. We work behind the scenes to build reliable infrastructure that can support modern households & businesses now and in the years ahead.

In Western Canada, F3 Networks has worked with major service providers, on large-scale fiber expansion projects.

What This Means for You

This upgrade is bringing new fiber infrastructure to your neighbourhood, with no cost or
commitment required from owners.

No Cost to You

There is no cost to
owners for this work.

No Commitment Required

You do not need to sign up for service or change your current provider.

Future Proofed

Future-Proofed Connectivity

The network is being built to support your community’s connectivity needs over time.

Built for Modern Households & Businesses

It can support everyday needs like streaming, video calls, remote work, gaming, and smart devices.

What Residents or businesses Can Expect

Construction near your home can raise questions, and F3 Networks is here to help keep you informed throughout the process.
Here’s what the community can generally expect during construction:

Residents
businesses

01

Work typically follows existing utility routes where possible

02

Existing copper or fiber services on your property are not
being replaced

03

This is not a 5G or wireless equipment project

04

Some areas may require temporary markings, flags, or paint to
identify utilities

05

If an area is disturbed during installation, it will be restored after the work is complete

06

If driveway cutting is required, it is usually limited and
repaired afterward

Construction Notice

Current Construction Updates

Live Project Details

Neighbourhood

Port Dalhousie

Expected timelines

April 12 - May 24, 2026

Location & Status
Location

Main Street from Lake Street to Geneva Street

Status Update

Crews are active in this area carrying out fiber installation and related construction work. Traffic and pedestrian access will be maintained where possible.

Construction Notice

Current Construction Updates

Live Project Details

Neighbourhood

Niagara St & Russell Ave

Expected timelines

April 20 - September 23, 2026

Location & Status

Location

Russell Ave, Junkin St, Linden St, Wiley St, Fitzgerald St, Niagara St

Status Update

Crews are working in this area now. Drilling is underway on Junkin St, Linden St, Wiley St and Fitzgerald St to install underground conduit, with site preparation continuing along Niagara St. Backfill and surface restoration on Russell Ave may still be in progress. Traffic and pedestrian access will be maintained where possible.

Live Project Details

Neighbourhood

Niagara St & Russell Ave

Expected timelines

April 20 - September 23, 2026

Location & Status

Location

Russell Ave, Junkin St, Linden St, Wiley St, Fitzgerald St, Niagara St

Status Update

Crews are working in this area now. Drilling is underway on Junkin St, Linden St, Wiley St and Fitzgerald St to install underground conduit, with site preparation continuing along Niagara St. Backfill and surface restoration on Russell Ave may still be in progress. Traffic and pedestrian access will be maintained where possible.

Live Project Details

Neighbourhood

Carlton St & George St

Expected timelines

April 04 - July 31, 2026

Location & Status

Location

Henry St

Status NEW

Crews are active in this area carrying out fiber installation and related construction work. Traffic and pedestrian access will be maintained where possible.

Live Project Details

Neighbourhood

Niagara St & Welland Ave

Expected timelines

May 05 - July 31, 2026

Location & Status

Location

Niagara St, Maple St, Russell Ave

Live Project Details

Neighbourhood

Gerard St

Expected timelines

July 16, 2026 - To be confirmed

Location & Status

Location

Raymond St, Gerard St

Live Project Details

Neighbourhood

King St/Court St

Expected timelines

May 25, 2026 - To be confirmed

Location & Status

Location

Live Project Details

Neighbourhood

Henry St

Expected timelines

May 13, 2026 - To be confirmed

Location & Status

Location

Contact Us

Questions about construction, crews in your area, property access, or restoration? Residents can contact our team in one place for questions, updates, and support.

How To Reach Us

Note: Once we receive your message, our team will follow up within 2 business days.

Frequently Asked Questions

Who Is F3 Networks?

F3 Networks is a Canadian company that builds fiber infrastructure in local communities. F3 owns the infrastructure being installed and works with service providers that use the network.

This work is part of a community-wide fiber upgrade. F3 Networks is building infrastructure in the area to help support your community’s connectivity needs in the years ahead.

No. This installation is entirely new infrastructure and does not involve replacing your existing copper or fiber lines on your property.

In most cases, fiber installation follows the same path as existing utility services. Crews may need to locate utilities, mark routes, install conduit, and complete restoration after the work is finished. We aim to carry out this work safely and with as little disruption as possible.

No. This project is focused on installing underground fiber-optic cable. It is not a 5G or wireless equipment installation.

Installation can be completed using underground or aerial methods, depending on the area. In general, the process includes resident notification, utility locates, infrastructure installation in the right-of-way, and creating a connection point near the home.

In most cases, the impact is limited. Where installation requires markings, small access points, or minor disturbance, F3 aims to restore the property to the appropriate condition once work is complete.